Critical Path Analysis exam questions

1 question pack of real past exam questions with its mark scheme. Answer every question without notes, then mark your answers line by line against the mark scheme.

About A Level Further Maths Critical Path Analysis

Critical Path Analysis is part of Decision Maths in A Level Further Maths. These questions suit AQA, Edexcel, OCR A, OCR B (MEI) and CCEA A Level Further Maths students. Answer the pack without notes, then mark every line against the model answers and redo the questions you dropped marks on.

What you need to know

  • Networks Activity on arc and dummies.
  • Times Early and late event times.
  • Scheduling Gantt charts and resource levelling.

Common mistakes in Critical Path Analysis

  • Missing dummy activities.
  • Wrong backward pass.

Try two Critical Path Analysis exam-style questions

1. What is the float on critical activities? (1 mark)

Show the mark scheme answer

0

2. What does the backward pass find? (1 mark)

Show the mark scheme answer

Late event times

Critical Path Analysis FAQs

Which exam boards include Critical Path Analysis?

These questions suit AQA, Edexcel, OCR A, OCR B (MEI) and CCEA A Level Further Maths.

Is Critical Path Analysis pure, mechanics or statistics?

Critical Path Analysis is part of Decision Maths.

How should I use these Critical Path Analysis questions?

Answer every question without notes, then check each line against the model answers and redo any you got wrong.